Page 568 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
P. 568

The Post-Shipment Phase: Installation, Pre-Commissioning, Commissioning and Start-up Best Practices  Best Practice 1 0.6

                                                                                    Fig 10.6.20   Shaft alignment e preliminary
                                                                                    considerations




























                                                                                Fig 10.6.21   Shaft alignment e alignment change
                                                                                limits when connecting piping


























                                                                   Why? It is costly, exposes the plant to possible safety
                                       1
                I  Confirm excessive pipe stress (refer to Figure 10.6.24). Also  problems and can result in a process unit shutdown. Usually,
                 confirm pipe bolting can be removed without a ‘come along’  it should be planned for a T&I. I have found that the
               II Walk piping system and confirm proper installation per piping  guidelines in Figure 10.6.24 provide the best probability of
                 isometrics                                        implementation.
                  Proper pipe support shims
                  Spring supports free to move
                  No obvious pipe misalignment
               III  Correct excessive pipe stress by: 2
                  Attempting rebolting at the next flange             1. Float pipe to machine. Machine is not a pipe support
                  Using ‘Dutchman’ with flexitallic gaskets (each side)  2. Lock pins on spring or pipe supports adjacent to machinery
                  Heating of pipe for alignment                        kept in place until system filled
                  Pipe modification at next T&I                       3. Flanges parallel on machined surfaces and no come alongs!
                     1
                Notes:  Work permits required                          (Bolts can be removed without excessive force)
               2 All items in III must be confirmed correct per Box 10.6.23.  4. Flange faces within 0.0010"

              Fig 10.6.22   Suggested excess pipe stress solution procedure  Fig 10.6.23   Pipe considerations

                                                                                                               539
   563   564   565   566   567   568   569   570   571   572   573