Page 599 - Subyek Teknik Mesin - Forsthoffers Best Practice Handbook for Rotating Machinery by William E Forsthoffer
        P. 599
     Preventive and Predictive Maintenance Best Practices  Best Practice 1 1.6
               Best Practice 11.6
               Always perform transient oil system tests (main oil pump  did not properly respond during plant operation resulting in
               forced trip and aux. pump start without system instability  a unit shutdown on low oil pressure.
               or shut down) prior to shutdown to ensure optimum oil  If it is suspected, from past experience, that the transient test
               system operation and reliability.                   will not be successful it is recommended that advance engineering
                  These tests performed during equipment shutdown (at turn-  be performed for installation of a properly sized and instrumented
               arounds) do not duplicate operational characteristics and lead to false  dual stainless steel accumulator assembly during the turnaround.
               conclusions regarding system transient response.    See B.P. 7.14.
                  Follow the procedure noted below (see Supporting Material) im-
               mediately before the turnaround and take appropriate action to correct  Benchmarks
               issues during the turnaround.                       This best practice has been recommended since the late 1980s, to
                                                                   identify and resolve long term critical oil system reliability issues that
               Lessons Learned                                     had previously caused large unit revenue losses over the life of the
               Oil system transient tests performed during a turnaround  critical machinery train.
               have shown acceptable results only to find that the system
              B.P. 11.6. Supporting Material                       correctly such that all system design objectives have been
                                                                   obtained and that equipment reliability is optimized.
              Functional testing                                     One remaining factor to be proven is the successful operation
                                                                   of the system with the critical equipment unit in operation.
              Having satisfactorily installed and flushed the auxiliary system,  During initial start-up, it is recommended that the functional
              all auxiliary equipment should be functionally tested and all  test be re-performed with the unit operating. While this advice
              instruments and controls checked for proper setting prior to  may seem dangerous, unless the unit operators ensure that the
              operation of equipment. A functional test outline and procedure  subject system has the ability to totally protect critical equip-
              is included in the end of this section. We will highlight the major  ment while operating, auxiliary equipment will never be tested
              considerations of the procedure at this time.        while the unit is in operation.
                It is recommended that the console vendor and/or the  Remember, critical equipment is designed for 30 years or
              equipment purchaser prepare a detailed field functional test  greater life. The components that comprise the auxiliary system
              procedure and calibration check form. The format of this  are many and have characteristics that will change with time.
              procedure can follow the factory test procedure if this is ac-  Therefore, reliability of auxiliary systems can only be main-
              ceptable. As a minimum, the auxiliary system, bill of material,  tained if the systems are totally capable of on-line calibration
              and schematic should be thoroughly checked in order to in-  and functional checks. The functional pre-commission pro-
              clude the calibration and functional test of each major com-  cedure should be modified to include an on-line periodic func-
              ponent in the auxiliary system e that is, components on  tional checking procedure. Such a procedure is included at the
              consoles and at unit interfaces. A detailed record should be  end of this section.
              kept of this functional test procedure. This will help signifi-  At this point, we can clearly see that the major determination
              cantly during the operation of the unit. The test procedure  of continued equipment reliability rests with the operation,
              should be accomplished without the critical equipment running  calibration and maintenance of the equipment. In order to
              initially and then with the auxiliary system at design operation  assume maximum continued auxiliary equipment reliability,
              conditions as closely as possible. The functional test procedure  periodic on-line functional checks and calibrations must be
              should first require that all instrumentation is properly  performed. How can this be done? The only way is by
              calibrated before proceeding. Each specific functional test  convincing plant operations of the safety and reliability of the
              requirement should then be performed and results noted. If  procedure for on-line checking. This can be reinforced during
              they do not meet specified limits as noted, testing should stop  pre-commissioning by including operators in functional testing
              and components should be corrected at this point. Each step  checks and on-site training sessions to show the function of the
              should be followed thoroughly to ensure each component  system. A site training course modified for the specific equip-
              meets all requirements. It is recommended that operators  ment would prove immensely valuable in achieving those
              assigned to this particular unit assist in functional testing to  results.
              familiarize themselves with the operation of the system. In  Only by involving unit operators in the pre-start check ups
              addition, site training courses should be conducted prior to  can it be hoped to establish a field functional checking
              functional test to familiarize operators with system’s basic  procedure that will be utilized and followed through. Re-
              functions. This training, again, significantly increases un-  member, a pressure switch less than $400 in cost could cause
              derstanding of the equipment and ensures unit reliability.  equipment shutdown that could reduce on-site revenue on the
                Satisfactory acceptance of a functional test then ensures that  order of $1-2m U.S. dollars a day. The pressure switch selected
              the unit has been designed, manufactured, and installed  could be the best, the highest quality in the world, properly
                                                                                                               571
     	
