PROJECT PORTFOLIO SCORE CARD 19-17
100,0
90,0
80,0 76,0 60,0 63,0 67,0 68,0
Level of fulfilment 60,0 58,0
70,0
50,0
40,0
30,0
20,0
10,0
0,0
Project management Engineering Procurement Assembly Initial operation Pilot operation
FIGURE 19.8 Bar graph showing the status of internal processes.
TABLE 19.6 Target Values and Actions for Each Process
Target
Process Score Value Actions
Project management 57,8 60 Further training, create
project handbook, moderate
project start workshop,
moderate project close-
down workshop
Engineering 75,9 80 Set and check quality gates
for design review
Procurement/logistics 60,3 65 Integrate logistics process into
commercial process
Assembly/supervision 63,2 65 Include construction-site
management in the assembly
calculation
Initial operation/ 66,5 70 Keep an online construction
training diary
Pilot operation 67,8 70 Set and check quality gate
before planing the
performance of work package
TOTAL 64,9 68