19-14          MANAGEMENT OF THE PROJECT-ORIENTED COMPANY

        TABLE 19.3  Excerpt from Questionnaire
        Questions                                             Score

         1  Project management                           −−  −  0   +  ++
         1.1 Has the project manager been given the necessary authority to
            make decisions during the project assignment?
         1.2 Was a formal project assignment given during the
            assignment process?
         1.3 Will a project-start workshop be carried out with the
            project owner and the project team?
         1.4 Will the results of the project-start workshop be made into a
            project handbook and will this be signed off by the
            project owner?
         1.5 Will a periodic project controlling process with documented
            results and progress reports be established?
         1.6 Will a project close-down workshop be held and
            will lessons learned be documented and made available
            to other participants to the project?
         1.7 Does the project manager have adequate resources available
            throughout the performance of the project?
         1.8 Will quality attributes be continually monitored in the
            project management process (such as review meetings)?
         1.9 Will project coordination be promoted through permanent
            communication with project team members (meetings,
            individual discussions, e-mail)?
        1.10 Will risk management be carried out and documented in the
            project controlling process?
        1.11 Will claim management (changes) be promoted and
            documented in the project controlling process?
         2  Engineering                                  −−  −  0   +  ++
         2.1 Are the technical plans and documentation understandable
            (for example, short training time for assembly personnel)?
         2.2 Are the technical plans and documentation usable without
            corrections (for example complexity)?
         2.3 Is there enough technical know-how in the project pool

            around the project manager to provide support?
         2.4 Will the plans and documentation be prepared in such a
            way that few inquiries are needed?
         2.5 Are the facility and system completed without many changes
            in the technical customer specification?
         2.6 Are design review meetings in the project planning and are
            they carried out (such as milestones)?
         2.7 Are plans made in such a way that new customer wishes or
            necessary changes can be easily and quickly implemented?
         2.8 Are requests for planning changes carried out on time by
            the responsible members of the project pool?
         2.9 Are economic aspects of the on site assembly work
            adequately taken into consideration during project planning?
        2.10 Are requests for later acceptance tests considered during
            project planning?