Page 174 - Handbook of Electrical Engineering
P. 174

SWITCHGEAR AND MOTOR CONTROL CENTRES        157

                 Fuse manufacturers will usually offer advice on the most appropriate fuses to be used in a
           particular installation.


           7.5 SAFETY INTERLOCKING DEVICES

           Most switchboards and motor control centres are fitted with a variety of electrical and mechanical
           safety interlocking devices. Their purposes are to protect against for example:-

           • Withdrawing the switching device while it is carrying load or fault current.
           • Prevent the switching mechanism from being inserted when it is in its ‘on’ state.
           • Opening of access doors or panels before setting the switching device in its ‘off’ state.
           • Gaining physical access by human operators while the main conductors and contacts are energised.
           • Gaining access to the busbars when the switching devices have been withdrawn.
           • To prevent earthing switches from being closed on to live circuits or busbars.
           • Incorrect electrical operation of a complex process system in which various external devices,
             motors, pumps, etc. are intimately related. For example a lubrication oil pump must be running
             before the main drive motor is started on a pump or compressor.


                 Most of the above interlocks are mechanical latches, bolts and shutters. The last category
           is electrical functions using wired relays or electronic logic. Electrical interlocking is also used to
           ensure that certain closing and tripping functions take place in a particular sequence. The following
           examples are typical interlocking sequences:-
           • Energising a downstream switchboard through a transformer or plain interconnector. The upstream
             switching device is closed first. The downstream device is then closed. If either trips on fault then
             the other may be caused to trip by auxiliary circuits and relays.
           • ‘Two-out-of-three paralleling’ is a term used when a switchboard has two parallel feeders. It is
             the term given to a particular closing scheme applied to the two incoming and the busbar section
             circuit breaker. The feeders are usually transformers. The purpose of the scheme is to enable a
             no-break transfer of the feeders to take place, and to minimise the duration of a prospectively high
             fault level that may exist during the transfer. Auxiliary switches are fitted within the three circuit
             breakers to determine when all three are closed. As soon as the third circuit breaker is closed the
             fault level at the busbars will in most cases be too high, and a signal is then given to one of the
             circuit breakers to trip. A selector switch is sometimes used to choose which of the three will
             trip. Some installations use a timer relay to delay the automatic tripping action, and the time delay
             setting is typically 0.5 to 2.0 seconds. This scheme is not used for all dual feeder switchboards,
             but is common practice with low voltage switchboards.
           • Where a situation can arise that two supplies could be switched in parallel, then it is necessary
             to check that they are in synchronism and come from the same source, e.g. either side of an
             upstream switchboard. Checking can be arranged in one of two methods, or a combination of both
             methods. The first method uses auxiliary switches on the upstream circuit breakers, usually the
             busbar section circuit breakers. These auxiliary switches give a signal that its circuit breaker is
             open, thereby signalling that an unsynchronised supply will exist at the downstream location. The
             signal is used to prevent the three downstream circuit breakers being closed all at the same time,
             i.e. the ‘two-out-of-three paralleling’ scheme is inhibited from closing its third circuit breaker. The
   169   170   171   172   173   174   175   176   177   178   179