Page 448 - Handbook of Electrical Engineering
P. 448

COMPUTER BASED POWER MANAGEMENT SYSTEMS         437

                            Table 16.1. Relay devices and switchgear mechanism delay times

                          Device            Circuit breaker  Motor starter (contactor)
                                            delay (millisec)     delay (millisec)
                          Lockout relay        5                    5
                          Trip coil            5 to 10              5 to 10
                          Circuit breaker     80 to 120               –
                          Clearance time
                          Contractor             –                 50 to 100
                          Clearance time
                          Total delay         90 to 135            60 to 115


           detected by either the 86-G or the 86-T relay will trip the circuit breaker quickly and in about the
           same time duration.
                 When either the 86-G or the 86-T relay sends its signal to the circuit-breaker trip coil, time is
           taken before the circuit breaker begins to move and finally reach its fully open state. Table 16.1 shows
           the accumulation of time for typical high-voltage circuit breakers and motor contractor starters.
                 The PMS should be designed to monitor the status of all the main circuits in the system, the
           generator currents and powers, and all the outgoing currents and powers. The monitoring should be
           a cycle updating process, with a cycle period of at least five cycles of fundamental frequency e.g.
           100 to 250 millisec, to allow power transients to decay.
                 The monitoring process can be approached in two ways:-


           16.3.1.1 Precision approach

           Every circuit breaker, contactor and switching device in the high-voltage network is monitored for
           open and close status. In addition each circuit is provided with accurate active power transducers.
           Hence the PMS will be continually checking the active power balance in the network, and the actual
           consumption of each load. The PMS will be able to calculate exactly how much, and which, loads
           to shed when a generator trips due to a fault. The PMS can also add a small margin of power
           to each load to be shed so that the remaining generators are able to settle at a level similar to
           that before the faulted generator tripped. This is important when the pre-fault load factor of the
           generators is high i.e. approximately 90 to 95%, and it will prevent the transient power change in the
           remaining generators from causing a rise in gas-turbine power turbine temperature (frequently called
           the ‘operating temperature’).
                 This approach is the most accurate in terms of selecting which loads to shed and safeguarding
           the remaining generators.



           16.3.1.2 Approximate approach
           Every circuit breaker, contractor and switching device in the high-voltage network is monitored for
           open and close status. Each generator circuit is provided with an accurate active power transducer.
           Each load will be assigned an active power value from knowledge of the plant operating conditions
           and the nameplate rating of the load. The power transducers in the generator circuits are necessary
   443   444   445   446   447   448   449   450   451   452   453