Page 244 - How To Implement Lean Manufacturing
P. 244

222    Cha pte r  F i f tee n


                       We inquired about the OEE (Overall Equipment Effectiveness) for this line, and
                    they did not know, but we were able to discover the following information.
                        •  The production process consisted of two cells, operating in series.
                        •  Nearly all steps were simple manual assembly, with no major equipment until
                           final test.
                        •  They believed that line availability was well over 95 percent, close to 100
                           percent.
                        •  Operators were highly cross trained.
                        •  They had not had a stock out in over a month.
                        •  They had recently conducted line time studies, and had both line balancing charts
                           and standard combination work tables posted at the line for the product.
                        •  The entire plant had begun a lean initiative with some withdrawal kanbans and
                           had begun utilizing U-shaped manufacturing cells.
                        •  On this line, which produced 11 different models, they had also made an effort
                           to go to small lot production.
                        •  Within each cell they had a pull system in place, using kanban spaces, and the
                           operators would not forward the small lots unless the  kanban spaces were
                           empty.
                        •  All models were very similar, with over 90 percent of the component parts
                           being the same in all 11 models.
                        •  They described a small lot as 50 units, which was a tray.
                        •  Four trays were stacked in a small box and five small boxes were packed in a
                           larger box, for a total of 1000 units per box, and a typical shipping lot was 2000
                           units, or two large boxes on one pallet.
                        •  The customer demand was 10,000 units per week of a model mix, but since
                           changeover time was minimal, product mix was not an issue. Their problems
                           were threefold:
                           •  They could not produce to schedule and frequently missed shipments.
                           •  It took nearly twice the time.
                           •  It took nearly 70 percent extra labor to make a batch.



               Implementing the Prescription
                    We did some preliminary calculations and could easily understand some of the prob-
                    lems with production times and missed shipments. We could not yet explain the mag-
                    nitude of the extra labor required, however. Nor could we explain the need to work
                    eight days to produce five days of product.
                       Our approach was simple: We used the prescription outlined in Chap. 7 and we
                    decided to:
                        •  Synchronize supply to the customer, externally
                        •  Synchronize production, internally
   239   240   241   242   243   244   245   246   247   248   249