Page 245 - How To Implement Lean Manufacturing
P. 245

The Story of the Bravo Line    223


                        •  Create flow, including
                           • Establishing jidoka
                           •  Working to destroy batches
                        •  Establish a pull demand system

                    Synchronizing Supply to the Customer, Externally

                    The Takt Calculation
                    Demand was 10,000 units per week and the normal workweek was five days. Available
                    time was 24 hours per day, less a 30-minute lunch and two ten-minute breaks during
                    each of the three shifts, so we needed to produce 2000 units in 21.5 hours or generate a
                    39-second takt (21.5 × 3600/2000 = 38.7).
                       We checked the standard work combination table and it listed the cycle time as
                    28 seconds, but the line balancing studies appeared to be balanced to 25 seconds, so we
                    were baffled. First, why have two different cycle times? And second, if the cycle time
                    design is way less than takt, where are their problems? None of these questions could
                    be answered by the production supervisor or the process engineer—or anyone, for that
                    matter.

                    Synchronizing Production, Internally

                    The Basic Time and Balancing Studies
                    Even though they had done time studies, we redid them and found the following (as
                    shown in Fig. 15-1 and Fig. 15-2):
                       It is obvious they had made an effort to balance the cycle times to 25 seconds. We
                    could not find a basis for the 25 seconds, which was also the basis used in their planning
                    program. Ever since the original balancing was done six months earlier, problems had
                    occurred at both cells: at Station 1 in Cell 1, and Station 3 in Cell 2. As a result of these
                    problems, the work procedures had been modified but the balance chart and planning



                                              Cell 1 Time Study
                          40
                          35
                          30
                         Time (secs)  25                                         Their study
                          20
                                                                                 Our study
                          15
                          10
                           5
                           0
                               1    2     3    4    5     6    7    8     9
                                                Work station
                    FIGURE 15-1  Cell 1 balance chart, base case.
   240   241   242   243   244   245   246   247   248   249   250