Page 253 - How To Implement Lean Manufacturing
P. 253

The Story of the Bravo Line    231


                       The quantity control tools would have been much less effective if the quality control
                    issues had not been addressed. Taken all together, these tools then improved the perfor-
                    mance and the following occurred:

                        •  Quality was improved.
                        •  Lead times were reduced.
                        •  The cost to produce was reduced.

                       These three are the key objectives of Lean (again, refer to Chap. 20).

                    Application of “The Seven Techniques to Improve Flow”
                    We can employ seven basic techniques to reduce lead time and improve flow (see
                    Chap. 5). The following describes how they were applied to the Bravo Line.

                         1.  Reduce processing time  Here the major gain was achieved through the
                           reduction of defects and especially the reduction of rework, which had become
                           a part of the normal process. All the rework was simply non-value-added time.
                           Regarding the necessary work, here we did nothing to intentionally reduce the
                           processing time, although the time decreased as the operators became more
                           engaged in the process.
                         2.  Reduce piece wait time  This is the time a single piece is waiting to be
                           processed. Here the wait time is reduced by balancing, so the flow is synchronized.
                           In the original case, the cycle time was controlled by station one at 35 seconds,
                           so it took 35 seconds per station, times nine stations in Cell 1, to go through the
                           line, or 315 seconds, but only 207 seconds of work were performed. There were
                           108 seconds of wait time per piece caused by poor synchronization at Cell 1
                           alone. Again, in this case, the wait time was reduced, but it did not have a large
                           effect on lead time; however, it certainly made the process flow better. Following
                           the rebalancing of the work the gains achieved by reducing piece wait time
                           were found in manpower reductions.
                         3.  Reduce lot wait time  This is the time that a piece, within a lot, is waiting to be
                           processed. In this case, it is substantial and adds to the overall lead time, but
                           more importantly it adds to the first-piece lead time. This time is often overlooked
                           but is incredibly important. There will always be quality and production issues
                           and these issues must be uncovered quickly so they can be solved. If the lot wait
                           time is like the original case of the Bravo Line, it takes 3.9 hours for the first
                           pieces to get to final inspection. If a problem is found at final inspection, we now
                           have over 400 pieces to inspect and rework—for each problem we find. If the
                           lead time is shorter, the problems surface more quickly and we can react more
                           quickly. In our first run, we stopped five times in the first batch to correct
                           problems. This impact alone could have accounted for the huge excess in labor
                           expenses to run this line in the base case. To reduce lot wait times, shrink lot
                           sizes as we did here. The goal of minimum lot sizes is one-piece flow.
                         4.  Reduce process delays  This is the time an entire lot is waiting to be processed.
                           Often it is called queue time. Here we were able to reduce it from an average of
                           49 hours to 6 hours. This is caused by lack of synchronization and also by
                           transportation delays. Close coupling processes, or making them in the same
                           cell, mitigates this problem. Kanban can help this, but kanban is only a way to
   248   249   250   251   252   253   254   255   256   257   258