Page 262 - How To Implement Lean Manufacturing
P. 262

240    Cha pte r  S i x tee n


                    The OEE Initiative
                    It can be seen that Larana Manufacturing had completed steps 1, 2, and 3. Our evalua-
                    tions, especially the evaluation of the Five Precursors, told us clearly we were far from
                    being able to get deeply involved in true quantity control. Consequently, we chose to
                    implement an “OEE Initiative” because we had to work on improving the foundational
                    issues of quality control. This OEE Initiative effectively replaced steps 4 and 5. We then
                    set OEE goals and evaluated each line for the appropriate kaizen activities. For each line,
                    we developed an eight-week improvement plan, and these plans were executed by the
                    process engineers. To provide support, each week Kermit would review the progress
                    with each engineer, and once a month we had a formal OEE review, which took about
                    90 minutes. In the formal review, progress was checked, priorities were assessed, and
                    any needed resources were addressed. A Summary Eight-Week Status Report is shown
                    in Table 16-2, which is updated for Week 4 information.

                                        OEE Improvement Plans—Gains … Line 3
                                                                First 8-Week Plan
                                                   Period    Weeks 12–19
                                                                      Goal for   Deviation, *
                                                   Week 1    Week 4   End of    Goal—Wk 4
                                                   Actual    Actual   8 Weeks   Actual
                      Production Information
                      Total Units                  20,289    20,289   21,100    –811
                      Total Losses                 4,027     2,928    2,932     4
                      Total Salable Units          16,262    17,362   18,178    –816
                      Cycle-Time Improvements      5.20      5.20     5.00      –0.20
                      OEE Performance %            81.17%    85.84%   86.81%    –0.97%
                      Availability—%               87.38%    87.76%   91.60%    –3.84%
                      C/T Performance—%            94.74%    99.65%   96.30%    3.35%
                      Quality—%                    98.04%    98.16%   98.63%    –0.47%
                      OEE Losses/Units
                       Availability                2,563     2,483    1,866     –617
                       C/T Performance             1,067     71       777       706
                       Quality                     398       373      286       –87

                                                             This 8   Total to
                      Summary Gains                          Weeks    Date
                      Total Units/Shift                      0        0
                      Total Losses/Shift                     –1,100   –1,100
                      Total Salable Units/Shift              1,100    1,100

                    ∗ All positive deviations mean the goals were exceeded.
                    TABLE 16-2  Typical OEE Summary Status Report
   257   258   259   260   261   262   263   264   265   266   267