Page 300 - How To Implement Lean Manufacturing
P. 300

The Pr ecursors to Lean Not Handled Well     277


                    work day. Line OEE would need to be at 90 percent, and these levels had not been previ-
                    ously achieved.
                       We asked for the background on the recent increase to 36 units per day. We were
                    told the customer had demanded a 15 percent price reduction over two years and would
                    then give the plant additional demand. According to Miguel, the line was very profit-
                    able and management jumped at the chance with very little review, not even an update
                    of the Process Failure Mode Effects Analysis (PFMEA). Management was very confi-
                    dent the line would perform. Prior to the ramp-up, the customer returns were less than
                    500 PPM, on-time delivery was practically 100 percent, and the line name plate capacity
                    was adequate. It appeared to be a win-win situation, until they could not meet demand.
                    That problem cropped up almost immediately. In addition, with all the weekend over-
                    time and expediting, profits had eroded to practically zero and Miguel was convinced
                    they were not on the correct path to return to profitability.

                    We Investigate More, and Fix the Welding Machine, the First Problem
                    With this background, we did some digging and discovered the following. The welding
                    machine had numerous previous problems, but those problems were masked by excess
                    capacity in the line and the inventory situation, specifically the weekly pickups. Earlier,
                    they could have an off day or two and still be able to make up volume with the excess
                    capacity and even a little overtime. Also, it was only recently that they achieved the low
                    inventory levels. At higher inventory levels, this also helped mask the problem of the
                    welder’s poor reliability. We asked the technician in charge of solving this problem to
                    bring in the manufacturer’s rep for the welder. The welder’s rep readily confirmed that
                    the machine was probably capable of 30 units per day, but would surely overheat at
                    36 units per day. He suggested a minor upgrade to the cooling system, and for $1500 he
                    would expect greater than 99 percent reliability at our needed cycle times. The equip-
                    ment was ordered and installed. Table 17-2 shows the next 25 days of production.
                       In this five-week period, significant progress had been made. The welder did not
                    fail once. In addition:
                        •  Only one shipment was missed.
                        •  Production had improved by over three units per day.
                        •  The production variation shrank from 10.7 to 7.6 units.
                        •  Weekend work was significantly reduced.

                    The Second Problem, Sensor Stock Outs
                    Is Addressed
                                                                  Point of Clarity The  only
                    The second problem, the sensor stock outs, proved
                                                                  purpose of inventory is to
                    to be a little more slippery. The supplier was con-
                    tacted and he was doing all he could but was severely   protect sales, not production,
                                                                  but sales. So where should
                    stretched. His production facility was at capacity
                    and earlier he had informed the buyer, who did not   the inventory be located?
                    pass on this information. They had plans to increase  Inventory is a waste, so mini-
                    capacity, but any future increases were six months  mize the inventory cost, be it
                    away. It seemed the only viable short-term solution  in raw materials or finished
                    was to increase inventory levels to account for the  goods.
                    supplier’s variation. No one wanted to hear that.
   295   296   297   298   299   300   301   302   303   304   305