Coal-fired power plant Chapter 8 139
8.1.6 Equipment descriptions—Electrostatic precipitator sheet 1
Casing
Prefabricate wall and partition panels
Install anvil beams and antisneak age baffles on end frames/roof beams and
bottom baffles
Set partition and wall panels; stabilize with top-end frames and bottom-end
frames and intermittently with intermediate roof beams and supporting bot-
tom baffles
Install remaining intermediate roof beams and supporting bottom baffles
Square and plumb casing and began weld out
Complete casing welding, including the hoppers
Drop in preassembled hoppers with lower alignment frames and scaffolding
inside
Secure interior cross ties between roof beams, end frames, and bottom baffles
Hang inlet and outlet perforated plates
Preassemble and mount inlet and outlet plenums
Install inlet and outlet plenum cone sections
Install platforms, stairways, and ladders
Internals
Lift and set collecting plates into ESP
Join plate halves and attach plates to anvil beams
Do preliminary alignment of collecting plates
Preassemble discharge electrodes to high voltage frames
Lift high voltage frames and rest on collecting plates