Page 163 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 163

Coal-fired power plant Chapter  8 139


             8.1.6  Equipment descriptions—Electrostatic precipitator sheet 1

                Casing
                Prefabricate wall and partition panels
                Install anvil beams and antisneak age baffles on end frames/roof beams and
                bottom baffles
                Set partition and wall panels; stabilize with top-end frames and bottom-end
                frames and intermittently with intermediate roof beams and supporting bot-
                tom baffles
                Install remaining intermediate roof beams and supporting bottom baffles
                Square and plumb casing and began weld out
                Complete casing welding, including the hoppers
                Drop in preassembled hoppers with lower alignment frames and scaffolding
                inside
                Secure interior cross ties between roof beams, end frames, and bottom baffles
                Hang inlet and outlet perforated plates
                Preassemble and mount inlet and outlet plenums
                Install inlet and outlet plenum cone sections
                Install platforms, stairways, and ladders

                Internals
                Lift and set collecting plates into ESP
                Join plate halves and attach plates to anvil beams
                Do preliminary alignment of collecting plates
                Preassemble discharge electrodes to high voltage frames
                Lift high voltage frames and rest on collecting plates