Diesel power plant Chapter 7 133
7.47 Leaking channel set installation man hour
Facility—diesel power plant Actual Estimate
Description MH BM IW PF MH
Leaking channel WDAAA373661 1 set b 60 0 0 0 0
Leaking channel 2 WDAAA373663 2 set b 120 0 0 0 0
Leaking channel WDAAA373662 1 set b 80 0 0 0 0
Equipment installation man-hours 260 0 0 0 0
7.48 Man hour breakdown
7.48.1 Diesel power plant
Owner-furnished equipment
Direct craft man-hours Actual BM IW MW Estimate
Scope of work MH MH MH MH MH
4.6 Engines, couplings, and generators (B2) 4640 0 0 0 0
installation man-hours
4.9 Engines and aux platforms (A3) installation 4918 0 0 0 0
man-hours
4.12 Installation of pipe modules (B3) 1920 0 0 0 0
installation man-hours
4.15 Exhaust gas system (A11) installation 8020 0 0 0 0
man-hours
4.18 SCR and urea system (A13) installation 4518 0 0 0 0
man-hours
4.21 Cooling system (A10) installation 4134 0 0 0 0
man-hours
4.24 Intake air system (A11) installation 1472 0 0 0 0
man-hours
4.27 Fire water system (A14) installation 540 0 0 0 0
man-hours
4.30 Utility gas heating system estimate 560 0 0 0 0
installation man-hours
4.33 Lube oil system (pump and tanks) 1548 0 0 0 0
installation man-hour
4.36 Utility water installation man-hour 400 0 0 0 0
4.39 Secondary pipe support installation 3428 0 0 0 0
man-hours
4.42 Valves list installation man-hour 1089 0 0 0 0
4.45 Manometer/thermometer list installation 232 0 0 0 0
man-hour
4.48 Leaking channel set installation 260 0 0 0 0
man-hour