Page 154 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 154
Diesel power plant Chapter 7 129
7.34 Installation of utility water estimate
Description MH Qty Unit Qty Unit BM IW PF
Utility water 0 0 0
DAD/901 oil water transfer 40.0 1 EA 0 EA 0
pump 342#
Bolt down 4.0 4 EA 0 EA 0
NOx controller 4.0 14 EA 0 EA 0
SEN dosing box 4.0 14 EA 0 EA 0
IC pipe 2.0 14 LF 0 LF 0
Bolt up 3.1 9 EA 0 EA 0
Flex rubber bellows 4.0 17 EA 0 EA 0
Bolt up 3.2 34 EA 0 EA 0
7.35 Utility water installation man hour
Facility-diesel power plant Actual Estimate
Description MH BM IW PF MH
DAD/901 oil water transfer pump 342# 40 0 0 0 0
Bolt down 16 0 0 0 0
NOx controller 56 0 0 0 0
SEN dosing box 56 0 0 0 0
IC pipe 28 0 0 0 0
Bolt up 28 0 0 0 0
Flex rubber bellows 68 0 0 0 0
Bolt up 108 0 0 0 0
Equipment installation man-hours 400 0 0 0 0
7.36 Installation of secondary pipe support estimate data
Description MH Unit
Pipe support 8.0 EA
AB 1.0 EA
7.37 Installation of secondary pipe support estimate
Description MH Qty Unit Qty Unit BM IW PF
Secondary pipe support 0 0 0
Pipe support 8.0 291 EA 0 EA 0
AB 1.0 1100 EA 0 EA 0