Page 150 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 150
Diesel power plant Chapter 7 125
7.23 Intake air system (A11) installation man hours
Facility—diesel power plant Actual Estimate
Description MH BM IW PF MH
Intake air system (A11) estimate
Starting air bottle 9555# 160 0 0 0 0
Starting air compressor 80 0 0 0 0
Control and working air compressor unit 80 0 0 0 0
Expansion vessel 1708# 420 0 0 0 0
Charge air filter 2116# 420 0 0 0 0
Control air bottle 80 0 0 0 0
Air receiver 10050# 80 0 0 0 0
Bolt down 32 0 0 0 0
Flex hose 40 0 0 0 0
Bolt up 80 0 0 0 0
Equipment installation man-hours 1472 0 0 0 0
7.24 Installation of fire water system (A14) estimate data
Description MH Unit
Fire hose equipment 10.0 EA
Hose cabinet 10.0 EA
Fire water hydrant 10.0 EA
Extinguisher 4.0 EA
Mobile foam unit 10.0 EA
7.25 Installation of fire water system (A14) estimate
Description MH Qty Unit Qty Unit BM IW PF
Fire water system (A14) 0 0 0
estimate
Fire hose equipment 10.0 13 EA 0 EA 0
Hose cabinet 10.0 3 EA 0 EA 0
Fire water hydrant 10.0 26 EA 0 EA 0
Extinguisher 4.0 20 EA 0 EA 0
Mobile foam unit 10.0 4 EA 0 EA 0