128  Industrial process plant construction estimating and man-hour analysis


            7.32 Lube oil system (pump and tanks) installation man-hour

            Facility—diesel power plant          Actual        Estimate
            Description                          MH      BM   IW    PF   MH

            Lube oil service tank 1000gal        20      0    0     0    0
            Dress out—filling, suction, drain, vent, overflow  60  0  0  0  0
            Instrument                           20      0    0     0    0
            Clean lube oil tank 12,000gal        40      0    0     0    0
            Dress out—filling, suction, drain, vent, overflow  60  0  0  0  0
            Instrument                           24      0    0     0    0
            Flushing filter                      10      0    0     0    0
            Flex rubber bellows                  84      0    0     0    0
            Bolt up                              126     0    0     0    0
            Used lube oil tank 4000gal           20      0    0     0    0
            Dress out—filling, suction, drain, vent, overflow  60  0  0  0  0
            Instrument                           24      0    0     0    0
            Pipe bridge platform with stairs     360     0    0     0    0
            Pipe supports                        340     0    0     0    0
            AB (PS)                              260     0    0     0    0
            Lube oil pump unit                   40      0    0     0    0
            Equipment installation man-hours     1548    0    0     0    0




            7.33 Installation of utility water estimate data


            Description                               MH                Unit
            DAD/901 oil water transfer pump 342#      40.0              EA
            Bolt down                                 4.0               EA
            NOx controller                            4.0               EA
            SEN dosing box                            4.0               EA
            IC pipe                                   2.0               LF
            Bolt up                                   3.1               EA
            Flex rubber bellows                       4.0               EA
            Bolt up                                   3.2               EA