124 Industrial process plant construction estimating and man-hour analysis
7.21 Installation of intake air system (A11) estimate data
Description MH Unit
Starting air bottle 9555# 40.0 EA
Starting air compressor 40.0 EA
Control and working air compressor unit 40.0 EA
Expansion vessel 1708# 30.0 EA
Charge air filter 2116# 30.0 EA
Control air bottle 40.0 EA
Air receiver 10050# 40.0 EA
Bolt down 2.7 EA
Flex hose 2.0 EA
Bolt up 2.0 EA
7.22 Installation of intake air system (A11) estimate
Description MH Qty Unit Qty Unit BM IW PF
Intake air system (A11) estimate 0 0 0
Starting air bottle 9555# 40.0 4 EA 0 EA 0
Starting air compressor 40.0 2 EA 0 EA 0
Control and working air 40.0 2 EA 0 EA 0
compressor unit
Expansion vessel 1708# 30.0 14 EA 0 EA 0
Charge air filter 2116# 30.0 14 EA 0 EA 0
Control air bottle 40.0 2 EA 0 EA 0
Air receiver 10050# 40.0 2 EA 0 EA 0
Bolt down 2.7 12 EA 0 EA 0
Flex hose 2.0 20 EA 0 EA 0
Bolt up 2.0 40 EA 0 EA 0