Page 146 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 146

Diesel power plant Chapter  7 121


             7.15 Installation of SCR and urea system (A13) estimate data

             Description                                  MH             Unit
             SCR                                          60             EA
             Walking platform (attach to SCR)             40             SF
             Silencer                                     10             EA
             Bolt up to silencer                          11             EA
             26 Reactor mixing pipe                       47             LF
               00
             26 Bolt up                                   19             EA
               00
             Silencers 2354#                              10             EA
             Silencer support structure with platform
              Beams                                       2              EA
              X-brace                                     4              EA
              AB                                          3              EA
              Caged ladder                                10             LF
              Platform                                    10             SF
              Railing                                     4              LF
              Column                                      6              EA
             Urea tank 13  36 35,700gal                   50             EA
                      0
                          0
             Dress out—filling, suction, drain, vent, overflow  60       EA
             Instruments                                  4              EA
             Bolt down                                    4              EA
             Urea pump rack                               10             EA
             Urea pump control unit                       10             EA

             7.16 Installation of SCR and urea system (A13) estimate

             Description             MH    Qty  Unit  Qty  Unit  BM  IW   PF
             SCR and urea system (A13)                           0   0    0
             SCR                     60.0  14   EA    0    EA        0
             Walking platform (attach to SCR)  40.0  14  SF  0  SF   0
             Silencer                10.0  14   EA    0    EA        0
             Bolt up to silencer     11.4  14   EA    0    EA             0
             26 Reactor mixing pipe  47.1  14   LF    0    LF             0
               00
             26 Bolt up              18.6  28   EA    0    EA             0
               00
             Silencers 2354#         10.0  14   EA    0    EA        0
             Silencer support structure with
             platform
              Beams                  2.0   64   EA    0    EA        0
              X-brace                4.0   64   EA    0    EA        0
              AB                     2.5   16   EA    0    EA        0
              Caged ladder           10.0  4    LF    0    LF        0
              Platform               10.0  12   SF    0    SF        0
              Railing                4.0   36   LF    0    LF        0
              Column                 6.3   16   EA    0    EA        0
             Urea tank 13  36 35,700gal  50.0  2  EA  0    EA        0
                      0
                          0
             Dress out—filling, suction,  60.0  2  EA  0   EA        0
             drain, vent, overflow
             Instruments             4.0   12   EA    0    EA        0
             Bolt down               4.3   28   EA    0    EA        0
             Urea pump rack          10.0  14   EA    0    EA        0
             Urea pump control unit  10.0  14   EA    0    EA        0