Page 143 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 143
118 Industrial process plant construction estimating and man-hour analysis
7.12 Exhaust gas system (A11) estimate data
Description MH Unit
Exhaust gas system (A11)
Exhaust gas module 11680# 33.0 EA
Bolt down 1.1 EA
Service platform for injection pipe 22.0 EA
Double bellows 14.8 EA
Double multi-ply bellows 14.8 EA
Exhaust gas pipe
22 Straight run 24.3 LF
00
22 Bend 24.3 EA
00
22 Extension pieces with explosion pipe flange 24.3 EA
00
22 Field weld 23.8 EA
00
22 Flange weld 23.3 EA
00
22 Bolt up 9.0 EA
00
20 Exhaust explosion pipe 27.5 LF
00
20 Bolt up 10.1 EA
00
22 Fixed/sliding support 10.0 EA
00
22 Exhaust gas pipe (stack) 40.0 LF
00
22 Flange weld 14.3 EA
00
22 Bolt up 50.0 EA
00
20 Rupture disk 10.0 EA
00
Support platform at explosion pipe
Beams 2.0 EA
X-brace 4.1 EA
AB 2.5 EA
Caged ladder 10.0 EA
Platform 10.0 EA
Railing 10.0 LF
Expansion joint 10.0 EA