Page 147 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 147

122  Industrial process plant construction estimating and man-hour analysis


            7.17 SCR and urea system (A13) installation man-hours

            Facility-Diesel Power Plant          Actual        Estimate
            Description                          MH      BM   IW    PF   MH

            SCR                                  840     0    0     0    0
            Walking platform (attach to SCR)     560     0    0     0    0
            Silencer                             140     0    0     0    0
            Bolt up to silencer                  160     0    0     0    0
            26 Reactor mixing pipe               660     0    0     0    0
              00
            26 Bolt up                           520     0    0     0    0
              00
            Silencers 2354#                      140     0    0     0    0
            Silencer support structure with platform
              Beams                              128     0    0     0    0
              X-brace                            258     0    0     0    0
              AB                                 40      0    0     0    0
              Caged ladder                       40      0    0     0    0
              Platform                           120     0    0     0    0
              Railing                            144     0    0     0    0
              Column                             100     0    0     0    0
            Urea tank 13  36 35,700gal           100     0    0     0    0
                         0
                     0
            Dress out—filling, suction, drain, vent, overflow  120  0  0  0  0
            Instruments                          48      0    0     0    0
            Bolt down                            120     0    0     0    0
            Urea pump rack                       140     0    0     0    0
            Urea pump control unit               140     0    0     0    0
            Equipment installation man-hours     4518    0    0     0    0



            7.18 Installation of cooling system (A10) estimate data


            Description                                  MH             Unit
            LT radiator                                  8.8            EA
            VEA 901 maintenance water tank 10890#        20.0           EA
            Bolt down                                    2.0            EA
            Dress out—filling, suction, drain, vent, overflow  20.0     EA
            VEA 011 expansion vessel 628#                10.0           EA
            Instrument air bottle                        10.0           EA
            Air supply unit                              20.0           EA
            TSB air supply vessel                        20.0           EA
            Bolt down                                    2.0            EA
            Support structure
              Legs-columns                               2.3            EA
              Beams                                      2.0            EA
              Connections                                1.5            EA
              Bolt down—AB                               1.0            EA
              Platform                                   10.0           SF
              Handrail at ends                           2.0            LF
              Handrail at sides                          2.0            LF