Diesel power plant Chapter 7 127
7.30 Installation of lube oil system (pump and tanks)
estimate data
Description MH Unit
Lube oil service tank 1000gal 20.0 EA
Dress out—filling, suction, drain, vent, overflow 60.0 EA
Instrument 4.0 EA
Clean lube oil tank 12,000gal 40.0 EA
Dress out—filling, suction, drain, vent, overflow 60.0 EA
Instrument 4.0 EA
Flushing filter 10.0 EA
Flex rubber bellows 4.0 EA
Bolt up 3.0 EA
Used lube oil tank 4000gal 20.0 EA
Dress out—filling, suction, drain, vent, overflow 60.0 EA
Instrument 4.0 EA
Pipe bridge platform with stairs 360.0 EA
Pipe supports 10.3 EA
AB (PS) 2.1 EA
Lube oil pump unit 40.0 EA
Bolt down 4.0 EA
7.31 Installation of lube oil system (pump and tanks) estimate
Description MH Qty Unit Qty Unit IW
Lube oil system (pump and tanks) 0
Lube oil service tank 1000gal 20.0 1 EA 0 EA 0
Dress out—filling, suction, drain, vent, 60.0 1 EA 0 EA 0
overflow
Instrument 4.0 5 EA 0 EA 0
Clean lube oil tank 12,000gal 40.0 1 EA 0 EA 0
Dress out—filling, suction, drain, vent, 60.0 1 EA 0 EA 0
overflow
Instrument 4.0 6 EA 0 EA 0
Flushing filter 10.0 1 EA 0 EA 0
Flex rubber bellows 4.0 21 EA 0 EA 0
Bolt up 3.0 42 EA 0 EA 0
Used lube oil tank 4000gal 20.0 1 EA 0 EA 0
Dress out—filling, suction, drain, vent, 60.0 1 EA 0 EA 0
overflow
Instrument 4.0 6 EA 0 EA 0
Pipe bridge platform with stairs 360.0 1 EA 0 EA 0
Pipe supports 10.3 33 EA 0 EA 0
AB (PS) 2.1 122 EA 0 EA 0
Lube oil pump unit 40.0 1 EA 0 EA 0
Bolt down 4.0 4 EA 0 EA 0