132 Industrial process plant construction estimating and man-hour analysis
7.42 Installation of manometer/thermometer list estimate data
Description MH Unit
Manometer 2.0 EA
Thermometer 2.0 EA
7.43 Installation of manometer/thermometer list estimate
Description MH Qty Unit Qty Unit BM IW PF
Manometer/thermometer list 0 0 0
Manometer 2.0 60 EA 0 EA 0
Thermometer 2.0 56 EA 0 EA 0
7.44 Manometer/thermometer list installation man hour
Facility—diesel power plant Actual Estimate
Description MH BM IW PF MH
Manometer 120 0 0 0 0
Thermometer 112 0 0 0 0
Equipment installation man-hours 232 0 0 0 0
7.45 Leaking channel set estimate data
Description MH Unit
Leaking channel WDAAA373661 1 set b 60.0 EA
Leaking channel 2 WDAAA373663 2 set b 60.0 EA
Leaking channel WDAAA373662 1 set b 80.0 EA
7.46 Leaking channel set estimate
Description MH Qty Unit Qty Unit BM IW PF
Leaking channel set 0 0 0
Leaking channel 60.0 1 EA 0 EA 0
WDAAA373661 1 set b
Leaking channel 2 60.0 2 EA 0 EA 0
WDAAA373663 2 set b
Leaking channel 80.0 1 EA 0 EA 0
WDAAA373662 1 set b