7.26 Fire water system (A14) installation man hours
Facility—diesel power plant Actual Estimate
Description MH BM IW PF MH
Fire hose equipment 130 0 0 0 0
Hose cabinet 30 0 0 0 0
Fire water hydrant 260 0 0 0 0
Extinguisher 80 0 0 0 0
Mobile foam unit 40 0 0 0 0
Equipment installation man-hours 540 0 0 0 0
7.27 Installation of utility gas heating system estimate data
Description MH Unit
Gas regulating unit 30.0 EA
Fuel oil unit 20.0 EA
Bolt up 4.0 EA
7.28 Installation of utility gas heating system estimate
Description MH Qty Unit Qty Unit BM IW PF
Utility gas heating system 0 0 0
estimate
Gas regulating unit 30.0 14 EA 0 EA 0
Fuel oil unit 20.0 5 EA 0 EA 0
Bolt up 4.0 10 EA 0 EA 0
7.29 Utility gas heating system estimate installation man hours
Facility—diesel power plant Actual Estimate
Description MH BM IW PF MH
Gas regulating unit 420 0 0 0 0
Fuel oil unit 100 0 0 0 0
Bolt up 40 0 0 0 0
Equipment installation man-hours 560 0 0 0 0