Page 144 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 144

Diesel power plant Chapter  7 119


             7.13 Exhaust gas system (A11) estimate

             Description             MH    Qty  Unit  Qty  Unit  BM  IW   PF
             Exhaust gas system (A11)                            0   0    0
             Exhaust gas module 11680#  33.0  14  EA  0    EA        0
             Bolt down               1.1   224  EA    0    EA        0
             Service platform for injection  22.0  14  EA  0  EA     0
             pipe
             Double bellows          14.8  16   EA    0    EA        0
             Double multi-ply bellows  14.8  3  EA    0    EA        0
             Exhaust gas pipe
              22 Straight run        24.3  14   LF    0    LF             0
                00
              22 Bend                24.3  14   EA    0    EA             0
                00
              22 Extension pieces with  24.3  14  EA  0    EA             0
                00
              explosion pipe flange
              22 Field weld          23.8  16   EA    0    EA             0
                00
              22 Flange weld         23.3  48   EA    0    EA             0
                00
              22 Bolt up             9.0   80   EA    0    EA             0
                00
              20 Exhaust explosion pipe  27.5  8  LF  0    LF             0
                00
              20 Bolt up             10.1  8    EA    0    EA             0
                00
              22 Fixed/sliding support  10.0  28  EA  0    EA             0
                00
              22 Exhaust gas pipe (stack)  40.0  14  LF  0  LF            0
                00
              22 Flange weld         14.3  14   EA    0    EA             0
                00
              22 Bolt up             50.0  14   EA    0    EA             0
                00
              20 Rupture disk        10.0  8    EA    0    EA             0
                00
             Support platform at explosion
             pipe
              Beams                  2.0   256  EA    0    EA        0
              X-brace                4.1   32   EA    0    EA        0
              AB                     2.5   32   EA    0    EA        0
              Caged ladder           10.0  8    EA    0    EA        0
              Platform               10.0  8    EA    0    EA        0
              Railing                10.0  24   LF    0    LF        0
             Expansion joint         10.0  24   EA    0    EA        0
   139   140   141   142   143   144   145   146   147   148   149