Page 141 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 141
116 Industrial process plant construction estimating and man-hour analysis
7.7 Engines and Aux platforms (A3) estimate
Description MH Qty Unit Qty Unit BM IW PF
Engine and auxiliary platforms 0 0 0
(A3)
Extension platform legs 1.7 168 EA 0 EA 0
Handrail 0.6 672 LF 0 LF 0
Sleeve single 0.1 1708 EA 0 EA 0
Sleeve double 1.4 28 EA 0 EA 0
Platform frame 4.8 84 EA 0 EA 0
Platform legs 2.7 112 EA 0 EA 0
Stair 4.5 84 EA 0 EA 0
Stair railing 2.3 168 LF 0 LF 0
Grating 1.0 138 SF 0 SF 0
Ventilation unit (engine hall/ 10.0 32 EA 0 EA 0
aux area)
Engine auxiliary module 44.3 14 EA 0 EA 0
Stair with handrail 22.9 14 EA 0 EA 0
20 Charge air pipe 4.3 28 LF 0 LF 0
00
20 Field weld 20.0 14 EA 0 EA 0
00
20 Flange weld 19.3 28 EA 0 EA 0
00
20 Bolt up 8.6 28 EA 0 EA 0
00
7.8 Engines and Aux platforms (A3) installation man-hours
Facility—diesel power plant Actual Estimate
Description MH BM IW PF MH
Extension platform legs 280 0 0 0 0
Handrail 380 0 0 0 0
Sleeve single 180 0 0 0 0
Sleeve double 40 0 0 0 0
Platform frame 400 0 0 0 0
Platform legs 300 0 0 0 0
Stair 380 0 0 0 0
Stair railing 380 0 0 0 0
Grating 140 0 0 0 0
Ventilation unit (engine hall/aux area) 320 0 0 0 0
Engine auxiliary module 620 0 0 0 0
Stair with handrail 320 0 0 0 0
00
20 Charge air pipe 120 0 0 0 0
20 Field weld 280 0 0 0 0
00
20 Flange weld 540 0 0 0 0
00
20 Bolt up 240 0 0 0 0
00
Equipment installation man-hours 4918 0 0 0 0