6.14 FD fan estimate data
6.14.1 FD fan sheet 1
Description MH Unit
Fans
Install sole and baseplates 2.0 EA
Attach fan to foundation-bolted connection 0.4 EA
FD fan
Set fan housing split 6.0 EA
Set impeller assembly/shaft 8.0 EA
Alignment fan bearings 16.0 EA
Seal weld housing inside/outside 20.0 JOB
Weld inlet cones and stud rings 6.0 JOB
Weld shaft seal stud rings 6.0 JOB
Coupling alignment 14.0 JOB
Install damper 16.0 EA
Steam coil air heater 28.5 Ton
6.15 FD fan installation estimate
6.15.1 FD fan sheet 1
Historical Estimate
MH Unit Qty BM MW
Set and assemble FD fan 0 0
Install sole and baseplates 2.0 EA 0 0
Set fan housing split 6.0 EA 0 0
Set impeller assembly/shaft 8.0 EA 0 0
Alignment fan bearings 16.0 EA 0 0
Seal weld housing inside/outside 20.0 JOB 0 0
Weld inlet cones and stud rings 6.0 JOB 0 0
Weld shaft seal stud rings 6.0 JOB 0 0
Coupling alignment 14.0 JOB 0 0
Install damper 16.0 EA 0 0
Attach fan to foundation-bolted connection 0.4 EA 0 0
Steam coil air heater 28.5 Ton 0 0