114  Industrial process plant construction estimating and man-hour analysis


            7.2 General scope of field work required for diesel power plant
            7.2.1 Scope of work-field erection

               Engines, couplings, and generators (B2)
               Engine and auxiliary platforms (A3)
               Pipe modules (B3)
               Exhaust gas system (A11)
               Selective catalytic reduction (SCR) and urea system (A13)
               Cooling system (A10)
               Intake air system (A11)
               Fire water system (A14)
               Utility gas heating system
               Lube oil system (pump and tanks)
               Utility water
               Secondary pipe support, material from water for injection (WFI)
               Valves list
               Manometer/thermometer list



            7.3 Engines, couplings, and generators (B2) estimate data

            Description                               MH                Unit
            Engines, couplings, and generators (B2)
            Engine generator set 296962#              199.4             EA
            Spring element                            3.3               EA
            Anchoring plate with anchor bolt (AB)     3.3               EA




            7.4 Engines, couplings, and generators (B2) estimate

            Description                 MH     Qty  Unit  Qty  Unit  BM  IW
            Engines, couplings, and generators                      0    0
            (B2)
            Engine generator set 296962#  199.4  14  EA  0     EA        0
            Spring element              3.3    280  EA   0     EA        0
            Anchoring plate with AB     3.3    280  EA   0     EA        0