Page 135 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 135

Industrial package boiler Chapter  6 109


             6.12 Air heater installation man-hours

                                               Estimated BM         Actual BM
             Support steel                     0                    0
             Tubular air heater modules        0                    0
             Plenum                            0                    0
             Erect interconnecting ductwork    0                    0
             Air heater installation man-hours  0                   0



             6.13 General scope of field work required for FD fan

             6.13.1 Fans
             Perform all millwright work for the four fans. Alignment and grouting.


             FD fan

                Install FD fan
                Work scope:
                Set housing and inlet box
                Set shaft and inlet cones
                Install motor sole plates
                Set inlet damper and damper drive
                Set motor
                Set inlet silencer
                Lubrication
                Laser alignment
                Final dowelling
                Grouting of bearings and motor