7.9 Installation of pipe modules (B3) estimate data
Description MH Unit
Pipe module 11.5 EA
Bellows 5.4 EA
Bellows (bolt up) 3.8 EA
2.5 Rubber bellows (bolt up) 1.2 EA
00
IC pipe (1 ,1.5 ,2 ) 3.0 LF
00
00
00
7.10 Installation of pipe modules (B3) estimate
Description MH Qty Unit Qty Unit BM IW MW
Installation of pipe modules 0 0 0
(B3) estimate
Pipe module 11.5 14 EA 0.0 EA 0
Bellows 5.4 112 EA 0.0 EA 0
Bellows (bolt up) 3.8 224 EA 0.0 EA 0
2.5 Rubber bellows (bolt up) 1.2 56 EA 0.0 EA 0
00
IC pipe (1 ,1.5 ,2 ) 3.0 84 LF 0.0 LF 0
00
00
00
7.11 Installation of pipe modules (B3) installation man hours
Facility—diesel power plant Actual Estimate
Description MH BM IW MW MH
Pipe module 161 0 0 0 0
Bellows 600 0 0 0 0
Bellows (bolt up) 840 0 0 0 0
2.5 Rubber bellows (bolt up) 67 0 0 0 0
00
IC pipe (1 ,1.5 ,2 ) 252 0 0 0 0
00
00
00
Equipment installation man-hours 1920 0 0 0 0