Page 145 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 145
120 Industrial process plant construction estimating and man-hour analysis
7.14 Exhaust gas system (A11) installation man-hours
Facility—diesel power plant Actual Estimate
Description MH BM IW PF MH
Exhaust gas module 11680# 462 0 0 0 0
Bolt down 246 0 0 0 0
Service platform for injection pipe 308 0 0 0 0
Double bellows 236 0 0 0 0
Double multi-ply bellows 44 0 0 0 0
Exhaust gas pipe
22 Straight run 340 0 0 0 0
00
22 Bend 340 0 0 0 0
00
22 Extension pieces with explosion pipe flange 340 0 0 0 0
00
00
22 Field weld 380 0 0 0 0
00
22 Flange weld 1120 0 0 0 0
00
22 Bolt up 720 0 0 0 0
20 Exhaust explosion pipe 220 0 0 0 0
00
00
20 Bolt up 80 0 0 0 0
22 Fixed/sliding support 280 0 0 0 0
00
22 Exhaust gas pipe (stack) 560 0 0 0 0
00
22 Flange weld 200 0 0 0 0
00
22 Bolt up 700 0 0 0 0
00
20 Rupture disk 80 0 0 0 0
00
Support platform at explosion pipe
Beams 512 0 0 0 0
X-brace 130 0 0 0 0
AB 80 0 0 0 0
Caged ladder 80 0 0 0 0
Platform 80 0 0 0 0
Railing 240 0 0 0 0
Expansion joint 240 0 0 0 0
Equipment installation man-hours 8020 0 0 0 0