            7.14 Exhaust gas system (A11) installation man-hours

            Facility—diesel power plant           Actual       Estimate
            Description                           MH     BM    IW   PF   MH

            Exhaust gas module 11680#             462    0     0    0    0
            Bolt down                             246    0     0    0    0
            Service platform for injection pipe   308    0     0    0    0
            Double bellows                        236    0     0    0    0
            Double multi-ply bellows              44     0     0    0    0
            Exhaust gas pipe
              22 Straight run                     340    0     0    0    0
                00
              22 Bend                             340    0     0    0    0
                00
              22 Extension pieces with explosion pipe flange  340  0  0  0  0
                00
                00
              22 Field weld                       380    0     0    0    0
                00
              22 Flange weld                      1120   0     0    0    0
                00
              22 Bolt up                          720    0     0    0    0
              20 Exhaust explosion pipe           220    0     0    0    0
                00
                00
              20 Bolt up                          80     0     0    0    0
              22 Fixed/sliding support            280    0     0    0    0
                00
              22 Exhaust gas pipe (stack)         560    0     0    0    0
                00
              22 Flange weld                      200    0     0    0    0
                00
              22 Bolt up                          700    0     0    0    0
                00
              20 Rupture disk                     80     0     0    0    0
                00
            Support platform at explosion pipe
              Beams                               512    0     0    0    0
              X-brace                             130    0     0    0    0
              AB                                  80     0     0    0    0
              Caged ladder                        80     0     0    0    0
              Platform                            80     0     0    0    0
              Railing                             240    0     0    0    0
            Expansion joint                       240    0     0    0    0
            Equipment installation man-hours      8020   0     0    0    0