Page 28 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 28

xlii Introduction



              TABLE 11 Straight time and overtime additional MHs

              Other factors         MH       Factor
              Straight time
              additional MHs  MHs   17180    10%              1718
              Overtime      MHs     600      5%               30
              additional MHs                                         Percent
                                                                       of
                                                             19400     MH
                                                              2220   112.92%
                                 Range of impact      Use
              Other factors  Minor  Average  Severe   ST     OT
              Stacking of   10%     20%      30%      10%
              trades
              Morale and    5%      15%      30%
              attitude
              Reassignment  5%      10%      15%
              of manpower
              Stacking of   10%     20%      30%
              contractors
              own forces
              Dilution of   10%     15%      25%
              supervision
              Learning curve  5%    15%      30%
              Errors and    3%      5%       6%
              omissions
              Sharing       5%      15%      25%
              occupancy
              with owners
              operations
              Joint         5%      12%      20%             5%
              occupancy
              with other
              trades
              Interferences  5%     12%      30%
              with access to
              work site
              Deficient     10%     25%      35%
              materials
              delivery
              Fatigue       8%      10%      12%
   23   24   25   26   27   28   29   30   31   32   33