Page 28 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 28
xlii Introduction
TABLE 11 Straight time and overtime additional MHs
Other factors MH Factor
Straight time
additional MHs MHs 17180 10% 1718
Overtime MHs 600 5% 30
additional MHs Percent
of
19400 MH
2220 112.92%
Range of impact Use
Other factors Minor Average Severe ST OT
Stacking of 10% 20% 30% 10%
trades
Morale and 5% 15% 30%
attitude
Reassignment 5% 10% 15%
of manpower
Stacking of 10% 20% 30%
contractors
own forces
Dilution of 10% 15% 25%
supervision
Learning curve 5% 15% 30%
Errors and 3% 5% 6%
omissions
Sharing 5% 15% 25%
occupancy
with owners
operations
Joint 5% 12% 20% 5%
occupancy
with other
trades
Interferences 5% 12% 30%
with access to
work site
Deficient 10% 25% 35%
materials
delivery
Fatigue 8% 10% 12%