2 Industrial process plant construction estimating and man-hour analysis


            1.2 Graphic analysis of data
            A graph is a pictorial illustration of the relationship between variables. Assume
            for historical man-hour data that x is the independent variable and y is the
            dependent variable:



            1.2.1 Straight-line graph

                                            ð
                           y ¼ aþbx; Y ¼ aþ y y1Þ= x x1Þ xðÞ
                                                   ð
               where
               y¼dependent variable
               a¼intercept value along the y-axis at x¼0
               b¼slope, or the length of the rise divided by the length of the run;
               b¼(y y1)/(x x1)
               x¼independent or control variable