Page 34 - Industrial Process Plant Construction Estimating and Man Hour Analysis
P. 34
4 Industrial process plant construction estimating and man-hour analysis
MH/BW 10.00 y = 0.3339x + 0.2528… Series1
Linear (Series1)
0.00
0 5 10 15 20 25 30 Linear (Series1)
Pipe size
FIG. 1.2.1 CS BW-downhill.
2
The coefficient of determination, R , is exactly +1 and indicates a positive fit,
and all points lie exactly on the straight line. The relationship between X and Y
variables is such that as X increases and Y increases.