xliv Introduction


               Construction task: Boilermakers are connecting boiler tubes in the mud and
            steam drums.
               The work is expected to take several months, and the work sampling occurs
            at the start of the overall work.
               The study runs for 3 weeks for a crew of 14 boilermakers.
               Productivity is determined to be RF¼0.95. A total of N¼100 tubes are
            installed and N i ¼0.61 for an allowance of 20% per tube.
               Calculate input data:


                                        N i ¼ 0.61
                                        Ht¼ 3 14 40
                                        RF¼ 0.95
                                      PF&D¼ 1.2
                                        N¼ 100
            Hs¼(0.61) * (3 * 14 * 40) * (0.95) * (1.2)/100
                       Hs¼11.7 man-hours per tube