Page 295 -
P. 295

Master Data       277



                       for the top-level items in the BOM. Companies use MPS for the most critical
                       fi nished goods to ensure that resources and capacity are available for these
                       materials before they plan for other materials. MPS is an optional step in the
                       planning process and is usually followed by MRP, which completes the plan-
                       ning process for the remaining materials.

                       Lot Size Key
                       A lot size is the quantity of material that is specifi ed in the procurement pro-
                       posals generated by the material planning process. The lot size key specifi es
                       the procedure that is used to determine the lot size. A variety of procedures for
                       determining lot size are available. The most basic procedures are static lot-siz-
                       ing procedures, which specify a fi xed quantity based on either a predetermined
                       value (fi xed lot size) or the exact quantity required (lot-for-lot). For example,
                       when using the lot-for-lot procedure, if the calculated requirement for seats is
                       100, then the proposed order quantity is also 100. Period lot-sizing procedures
                       combine the requirements from multiple time periods, such as days or weeks,
                       into one lot. Optimum lot-sizing procedures take into account the costs of order-
                       ing and storing materials using techniques such as the economic order quantity
                       and economic production quantity calculations. For example, if the calculated
                       requirement for seats is 100, the proposed order quantity may be 500 if it is more
                       economical to purchase the seats in larger quantities. GBI uses the lot-for-lot
                       procedure to determine the lot size for all of its materials.


                       Scheduling Times
                       One task that must be performed by the planning process is to estimate the
                       time needed to procure the necessary materials. This calculation is based on
                       estimates of the time required to complete the various tasks that are included in
                       the material master and the product routing. Common time estimates include:
                          •  In-house production time, which is the time needed to produce the
                             material in house.

                          •  Planned delivery time, which is the time needed to obtain the mate-
                             rial if it is externally procured.
                          •  GR (goods receipt) processing time, which is the amount of time required
                             to place the received materials in storage so that they are ready for use.
                           In-house production time and the GR processing time are used to deter-
                       mine procurement time for internally procured materials. For externally pro-
                       cured materials, the planned delivery time and the GR processing time are used.
                           In-house production time is further divided into three time elements:
                       setup, processing, and interoperation. Recall the discussion of some of these
                       elements from Chapter 6.
                          •  Setup time is the time required to set up the work centers used in
                             production.
                          •  Processing time is the time required to complete operations in the
                             work centers.

                          •  Interoperation time is the time required to move materials from one
                             work center to another.






                                                                                                                 31/01/11   6:42 AM
          CH008.indd   277                                                                                       31/01/11   6:42 AM
          CH008.indd   277
   290   291   292   293   294   295   296   297   298   299   300