Page 182 - Mathematical Models and Algorithms for Power System Optimization
P. 182

Discrete Optimization for Reactive Power Planning 173

                    programming method are shown in Appendix A, and the method only changes one integer
                    each time.
               (3) The improvement procedure is then used to enhance this solution further, but no
                    improvement solution is found in this iteration. Thus, the solution obtained is only by the
                    approximation method, and first iteration ends with an integer solution in the line with
                    method of P and cost as 20.8. The integer solution has not been improved after it becomes
                    feasible.

               Second iteration:

               (1) With the integer solution from the first iteration as the starting point, approximation
                    integer programming method will be used to solve MILP problem after the solution is
                    linearized. Its integer solution changes in both the second and third stage. The obtained
                    integer solution is shown in line 5 and cost as 13.3.
               (2) As the integer solution improved algorithm that can change two integers each time is used,
                    the solution may be further improved. After several substeps of improvement, seven
                    installed nodes have been decreased to five installed nodes, that is, three installed adjacent
                    nodes 102, 106, and 107 are reduced to one installed node, 106. According to the result of
                    the iteration, the cost is 13.3 million yuan.

               Third to seventh iteration:

               With the integer solution of the second iteration as the starting point, the execution procedure is
               the same as that of the second iteration. However, from the third to seventh iteration, even
               continuous variable convergence and integer variables no longer change and improve, except
               for the number of reactive capacitor compensations at node 106, which was reduced by one
               bank in Step 3. This means that the integer solution obtained in the second iteration is a
               nonlinear power flow solution meeting problem P.

               The results of Cases 2–5 are briefly explained as follows. Cases 2 and 3 have the same voltage
               magnitude bounds of 0.95–1.05 and the same capacitor candidate set. The difference between
               Cases 2 and 3 is that Y i i 2 E C Þ is decreased and Y i i 2 N C Þ is increased in Case 3 as indicated by
                                                           ð
                                   ð
               mark superscript a in Table 6.2 in which both cases are successfully solved with almost the
               same CPU time.
               Cases 4 and 5 have the same conditions as Cases 2 and 3, respectively, except for voltage
               magnitude bounds of 0.97–1.03. The change of voltage bounds makes more violations occur,
               and more violations may cause larger computation time and more capacitor installations.
               Compared with Case 2, Case 4 is successfully solved with almost the same computation time,
               although more initial violations exist in Case 4 than in Case2. As for Case 5, the number of
               existing capacitor units is decreased, and it takes longer computation time to adjust new
               capacitor units.
   177   178   179   180   181   182   183   184   185   186   187