Page 185 - Mathematical Models and Algorithms for Power System Optimization
P. 185

176 Chapter 6

            considered in this program only include the static outages, such as transmission lines,
            transformers, or generator outages, not including some severe dynamic faults in the power
            system. This research discusses development of a computer algorithm, a multiple state
            algorithm, that can select one overall reactive power installation pattern that will satisfy system
            performance for both base state and contingency states. Most importantly, this algorithm needs
            only a little more computer storage than that of a single-state algorithm.
            As previously mentioned, VAR planning should provide a system with VAR equipment, which
            can experience the most severe state along with each possible state. The consideration of
            several contingency states of various load conditions (light, medium, and peak load) creates an
            enormous nonlinear mixed-integer optimization problem. For example, there are more than
            900 continuous variables and 120 integer variables for a 135 node system VAR planning
            problem under three contingencies.
            The goal of the reactive power planning problem is to find the minimum cost installation plan of
            new reactive power sources so that the system voltage is maintained within an acceptable range.
            The formulation of the multistate VAR planning problem must take into account the following
            two aspects:
            (1) The number of installed VAR sources takes an integer value.
            (2) The installed VAR sources must be sufficient even in contingency states or in anticipated
                 operating states.
            A consideration of multiple states, together with the discrete nature of VAR facilities, creates a
            large-scale nonlinear MIP problem. Because no general mathematical programming
            technique for solving such a problem exists, a new algorithm should be developed that can
            handle both the discrete nature of capacitor units and multiple states in power systems.
            In previous researches, the consideration of both the multiple states in power systems and the
            discrete nature of VAR facilities has not been well treated. In this section, based on the previous
            study, an approximate solution method for MIP problems is employed. Because the
            method is LP-based, it is efficient for large-scale problems.

            To take multiple states into account, a resource directive decomposition approach is used in the
            proposed algorithm. To apply the approach to the multistate VAR planning problem, the
            number of installed VAR sources is treated as “resources,” which are assigned to each state. If
            the value of a resource (installed VAR source) is fixed, the overall problem can be decomposed
            into mutually independent subproblems. This is because the multistate VAR planning problem
            has a special form of a block diagonal structure. Then subproblems are coordinated to
            give a minimum cost VAR installation pattern for the overall problem. This method takes into
            consideration the “cooperative” effect of a VAR source installation for multiple operating
            states. The states considered in this section include not only normal operating states but also
            such outages as transmission line outages, transformer outages, and generator outages.
   180   181   182   183   184   185   186   187   188   189   190