Page 128 - Orlicky's Material Requirements Planning
P. 128

CHAPTER 6      The Material Requirements Planning System                        107


           FIGURE 6-7
                                                               Period
           Timing of a gross
           requirement.         Gear (Parent)       1   2   3  4   5  6   7   8
                                Planned-Order Releases         80



                                Forging (Component)
                                Gross Requirements             80

        puter program that controls the requirements computation. The subject of lot sizing will
        be reviewed in Chapter 8.
             The general rule of MRP logic can be stated as follows: The mutual parent-compo-
        nent relationship of items on con tiguous product levels dictates that the net requirement
        on the parent level, as well as its coverage by a planned order, be computed before the
        gross requirement on the component level can be determined correctly. The tim ing of a
        gross requirement for a component item coincides with the timing of an order release
        planned for its parent, as shown in Figure 6-7.



                                      Item Lead Times
        Lead times of the individual inventory items are a complicating factor in the computa-
        tion of material requirements. The preceding example of net requirements determination
        for forgings, gears, and so on was oversimplified in ignoring, among other things, item
        lead times. It is these lead times that will determine the timing of releases and scheduled
        completions for the orders in question. Because a component-item order must be com-
        pleted before the parent-item order that will consume it can be started, the back-to-back
        lead times of the four items in the example make up the cumulative lead time, a sort of
        critical path that determines the earliest time that the end products could be built or,
        given the end-product schedule date, the latest time for the start of the lowest-level item
        order. Cumulative lead time is represented graphically in Figure 6-8. See also the discus-
        sion of lead time in Chapter 4.
             If the manufacturing lead times for the four items in the example were
             Forging blank D:         3 weeks
             Gear C:                  6 weeks
             Gearbox B:               2 weeks
             Transmission A:          1 week
                                     12 weeks (cumulative lead time)
        and assembly of the end product, truck X, were scheduled for a date arbi trarily desig-
        nated as week 50, component-order release dates and comple tion dates could be calcu-
        lated by successively subtracting the lead-time values from 50:
   123   124   125   126   127   128   129   130   131   132   133