Page 129 - Orlicky's Material Requirements Planning
P. 129

108                                                                 PART 2   Concepts


           FIGURE 6-8           Present                    Earliest Date
                                 Date                   Assembly of Truck X
           Cumulative lead
           time.               Level
                                                           Trans-
                                1
                                                          mission
                                2                    Gearbox
                                3             Gear
                                4   Forging

                                         Cumulative Lead Time
                                                                    Scheduled Date
                                                                   Assembly of Truck
                                         Latest Date
                                      Forging Order Start
                                                                     Trans-
                                1
                                                                    mission
                                2                              Gearbox
                                3                       Gear
                                4             Forging

                                                   Cumulative Lead Time

             Complete order for item A:     week 50
             Minus lead time of item A:     1 week
             Release order for item A:      week 49
             Complete order for item B:     week 49
             Minus lead time of item B:     2 weeks
             Release order for item B:      week 47

             Complete order for item C:     week 47
             Minus lead time of item C:     6 weeks
             Release order for item C:      week 41

             Complete order for item D:     week 41
             Minus lead time of item D:     3 weeks
             Release order for item D:      week 38

             The preceding release dates of parent orders would establish the timing of gross
        requirements for the respective component items, as illustrated in Figure 6-7. Because, in
        the example, none of the gross requirements can be fully satisfied from inventory, the tim-
        ing of net requirements for each of the items coincides with that of gross requirements.
        The timing of the orders providing coverage of net requirements is geared to the latter
        (for comple tion dates) and is a function of the respective lead times (for release dates). In