Page 167 - Orlicky's Material Requirements Planning
P. 167

146                                                                 PART 2   Concepts


        connection with manufactured inventory items, and the term setup covers all (fixed) costs
        of ordering. The reader should understand, however, that the logic on which these tech-
        niques are based is not limited to manufactured items. Where the cost of ordering pur-
        chased items is significant and/or where quantity discounts apply, any of the economics-
        oriented lot-sizing techniques can be used after appropriate modification. 1


                               Fixed Order Quantity (FOQ)
        An FOQ policy may be specified for any item under an MRP system, but in practice, it
        would be limited to selected items only, if used at all. This policy would be applicable to
        items with ordering cost sufficiently high to rule out ordering in net requirements quan-
        tities period by period. The FOQ specified for a given inventory item may be determined
        arbitrarily, or it can be based on intuitive/empirical factors. The quantity may reflect
        extraneous considerations, that is, facts not taken into account by any of the available lot-
        sizing algorithms. Such facts may be related to the capacities of certain facilities or
        processes, die life, packaging, storage, and so on. It is understood (and the MRP system
        would be programmed accordingly) that when using this lot-sizing rule, the order quan-
        tity will be increased if necessary to equal an unexpectedly high net requirement in the
        period the order is intended to cover. For example, if the FOQ were 60 and the earliest net
        requirement were 75, the planned-order quantity normally would be increased to 75
        because it would make little sense to generate two orders of 60 each for the same period.
        Note that this also applies to the EOQ, particularly where it is used as a fixed quantity
        repetitively ordered over a period of time (typically a year). An example of an FOQ of 60
        is provided in Figure 8-1. Note that in this and subsequent examples, the order quantities
        are not offset for lead time; that is, each quantity is shown under (keyed to) the earliest
        period it is intended to cover.

           FIGURE 8-1
                               Period                1   2   3  4   5   6  7   8   9  Total
           Fixed order
           quantity (60).      New Requirements      35 10      40     20   5  10 30  150
                               Planned-Order Coverage  60       60                60  180


                             Economic Order Quantity (EOQ)
        The EOQ formula was first derived by Ford W. Harris in 1915. It is the oldest technique
        in the field and is still an aid to sound planning when its limitations are recognized.
        Although it predated and was not intended for an MRP environment, it can be incorpo-
        rated easily into an MRP system if the user so wishes. Figure 8-2 shows EOQ coverage of
        the same net requirements as used in the preceding example.



        1  Purchasing (General Information Manual Form No. GH20-1149-1). New York: International Business Machines
         Corp., 1973, pp. 140–164.
   162   163   164   165   166   167   168   169   170   171   172