Page 170 - Orlicky's Material Requirements Planning
P. 170

CHAPTER 8   Lot Sizing                                                          149


           FIGURE 8-4
                               Period                 1  2   3   4  5   6   7  8   9  Total
           Fixed-period
           requirements.       New Requirements      35 10      40      20  5  10 30  150
                               Planned-Order Coverage  40       40     25      40     150

                               Period Order Quantity (POQ)

        This technique, sometimes called economic time cycle, is based on the logic of the classic
        EOQ modified for use in an environment of discrete period demand. Using known future
        demand as represented by the net requirements schedule of a given inventory item, the
        EOQ is computed through the standard formula to determine the number of orders per
        year that should be placed. The number of planning periods constituting a year then is
        divided by this quantity to determine the ordering interval. The POQ technique is iden-
        tical to the one just discussed except that the ordering interval is computed.
             Both these fixed-interval techniques avoid remnants in an effort to reduce inventory
        carrying cost. For this reason, the POQ approach is more effective than the EOQ approach
        because setup cost per year is the same but carrying cost will tend to be lower under
        POQ. A potential difficulty with this approach, however, lies in the possibility that dis-
        continuous net requirements will be distributed in such a way that the predetermined
        ordering interval will prove inoperative. This will happen when several of the periods
        coinciding with the ordering interval show zero requirements, thus forcing the POQ tech-
        nique to order fewer times per year than intended.
             Using the previous EOQ example and the annualized demand data, the POQ is
        determined as follows:

             EOQ   58
             Number of periods in a year   12
             Annual demand   200
             250/58   3.4 (orders per year)
             12/3.4   3.5 (ordering interval)

             The application of these results (assuming the interval alternates between 4 and 3)
        appears in Figure 8-5. Note that the third order covers only one period’s requirements
        because of insufficient horizon and will have to be recomputed (probably three times) in
        the future. In comparison with some of the other discrete lot-sizing techniques described
        below, the effectiveness of POQ, like that of the classic EOQ from which it springs, proves
        relatively low in the face of discontinuous, nonuniform demand.

           FIGURE 8-5
                               Period                 1  2   3   4  5   6   7  8   9  Total
           Period order
           quantity.           New Requirements      35 10      40      20  5  10 30  150
                               Planned-Order Coverage  85       35                30  150
   165   166   167   168   169   170   171   172   173   174   175