Page 168 - Orlicky's Material Requirements Planning
P. 168

CHAPTER 8   Lot Sizing                                                          147


           FIGURE 8-2
                               Period                 1  2   3   4  5   6   7  8   9  Total
           Economic order
           quantity.           New Requirements      35 10      40      20  5  10 30  150
                               Planned-Order Coverage  58       58                58  174


             These net requirements data will be carried over into subsequent examples of lot
        sizing to point up the differences in the performance of the various techniques. The peri-
        ods will be assumed to represent months, and the following cost data will be used
        throughout:
             Setup S            $100
             Unit cost C        $ 50
             Carrying cost I    0.24 per annum, $0.02 per period
             These cost data will facilitate calculations required in the use of some of the discrete
        lot-sizing techniques because the cost of carrying one unit of the inventory item for one
        period is $1. The EOQ calculation is as follows:


                          Q      2US      2   200   100    3,333   58
                                  IC         0.24   50
        where Q is the economic order quantity and U is the annual usage (in units). The value
        of U in this calculation was obtained by annualizing the nine-month demand (net
        requirements) of 150:

                                            9:150   12:X
                                       X   150   12/9   200

             In this case, the known future demand, rather than historical demand, was used as
        a basis for estimating annual usage. The example illustrates a problem all forward-look-
        ing lot-sizing techniques face, namely, a finite, or limited, planning horizon. In our exam-
        ple, an EOQ based on future demand would require a year’s demand data, but the sys-
        tem provides only nine months’ visibility. Most of the discrete lot-sizing techniques are
        not based on annual usage, but they assume a certain minimum visibility for each lot in
        the planned-order schedule, including the last one. In most cases, however, the quantity
        of the last lot is truncated by the proximity of the far edge of the planning horizon, as will
        be seen in subsequent examples.
             As to the effectiveness of the EOQ in a discrete-demand environment, a look at
        Figure 8-2 reveals that the first order quantity of 58 includes a “remnant” of 13 pieces that
        are carried in inventory in periods 1 through 3 to no purpose. Similarly, 6 pieces are car-
        ried unnecessarily in periods 4 through 7 owing to the size of the second lot. The ordering
        strategy provided by the EOQ approach (of ordering three times in quantities of 58) will
        be seen to be relatively poor in comparison with some of the other examples that follow.
   163   164   165   166   167   168   169   170   171   172   173