Page 171 - Orlicky's Material Requirements Planning
P. 171

150                                                                 PART 2   Concepts


                                   Least Unit Cost (LUC)

        This technique and the three that follow have certain things in common. All of them
        allow both the lot size and the ordering interval to vary. They share a common assump-
        tion of discrete inventory depletions at the beginning of each period, which means that a
        portion of each order, equal to the quantity of net requirements in the first period covered
        by the order, is consumed immediately on arrival in stock and thus incurs no inventory
        carrying charge. Inventory carrying cost, under all four of these lot-sizing methods, is
        computed on the basis of this assumption rather than on average inventories in each peri-
        od. All four of the techniques share the EOQ objective of minimizing the sum of setup
        and inventory carrying costs, but each of them employs a somewhat different attack.
             The LUC technique is best explained in terms of trial and error, and this approach is
        used here, although less primitive methods of computation do exist. In determining the
        order quantity, the LUC technique asks, in effect, whether this quantity should equal the
        first period’s net requirements or should be increased to cover the next period’s require-
        ments or the one after that, and so on. The decision is based on the unit cost (i.e., setup plus
        inventory carrying cost per unit) computed for each of the successive order quantities. The
        one with the least unit cost is chosen to be the lot size. Figure 8-6 shows the computation
        of the first lot. The next one is computed in identical fashion starting with period 4.
             The LUC is found at lot quantity 45, which will cover periods 1 and 2. The next
        order of 60 will cover periods 4 through 6, and the third order of 45 will cover periods 7
        through 9 (Figure 8-7). The limitation of the LUC approach lies in the fact that the tech-
        nique considers only one lot at a time. The unit cost varies, sometimes widely, from one
        lot to the next.
             Tradeoffs between consecutive lots sometimes could be made that would reduce the
        total cost of two or more lots. Our example contains such a situation: If the requirement
        in period 7 were added to the quantity of the second lot, its inventory carrying cost would
        increase by $15, but that of the next lot would decrease by $40. The lot-sizing technique
        described next attempts to overcome this flaw in LUC logic.

           FIGURE 8-6
                               Setup:  $100
                               Inventory carrying cost: $1 per unit per period
           Computation of
           least unit cost.            Net   Carried in  Prospec-  Carry cost, $
                                     require-  inventory  tive lot           Setup per  Unit
                               Period  ments  (periods)  size  For lot     Per unit  unit, $  cost, $
                                 1     35       0       35      0.00     0      2.86  2.86
                                 2     10       1       45     10.00    .22     2.22  2.44
                                 3      0       2                 0
                                 4     40       3       85    130.00   1.53     1.18  2.71

           FIGURE 8-7
                               Period                 1  2   3   4  5   6   7  8   9  Total
           Least unit cost.
                               New Requirements      35 10      40      20  5  10 30  150
                               Planned-Order Coverage  45       60         45         150
   166   167   168   169   170   171   172   173   174   175   176