Page 211 - Orlicky's Material Requirements Planning
P. 211

190                                                 PART 3      Managing with the MRP System


           FIGURE 10-8           Maximum

           Reducing the
                                  Behind
           queue to
                                 Schedule
           unneeded work.
                                    On
                                 Schedule
                                                    Minimum
                                 Ahead of           Ahead of
                                 Schedule           Schedule         Controlled
                                                                       Queue

                                 Way Ahead         Way Ahead         Way Ahead
                                of Schedule        of Schedule       of Schedule

                                    No                 No               No
                                Requirements       Requirements     Requirements


        WORK-IN-PROCESS REVISITED
        Work-in-process, in its relation to lead time, traditionally has been viewed as conforming
        to the following theorem:
                                             L   W/R

        where L   lead time (in days, weeks, or months)
                W   work-in-process inventory (in units, hours, or dollars)
                R   rate of output (per period of L, in units of W)

                            L   1,200 units/200 units per week   6 weeks
             The average lead time arrived at in this way is not always meaningful. When work-
        in-process is stratified by priority, the formula will be seen to be in need of modification.
        Average actual lead time is a function of the live portion of work-in-process and of the
        rate of production. For example:
             Active queues:                     800
             Deferred requirements:             300
             No requirements:                   100
             Total                             1,200

                       L   800 in (active) process/200 units per week   4 weeks

             Work-in-process and lead time codetermine one another. This is a kind of chicken-
        and-egg relationship, and the difficulty with the preceding equation is that it assumes
        that work-in-process (or, in another version, lead time) is given. In reality, of course,
        work-in-process is variable, and its level is a function of the relationship between input
   206   207   208   209   210   211   212   213   214   215   216