Page 460 - Orlicky's Material Requirements Planning
P. 460

438                                                 PART 4      Looking Backward and Forward


                stocking via a replenishment designation, but when there is a requirement for
                them, historically it has been difficult to maintain control and visibility. Ask most
                seasoned materials managers in major manufacturers and they can immediately
                recite a list of these types of components and the suppliers that make them. These
                components can be very difficult to manage, especially if they have long lead
                times and/or are sourced from a remote supplier. Without an effective way to
                manage these parts, there is a risk of major synchronization problems, costly
                expediting, and/or poor service-level performance.
                  Figure 26-3 is a conceptual picture of how LTM parts work. In this case, the
                part has a 60-day lead time. The last third of that lead time becomes the LTM alert
                zone. In this case, the LTM alert zone is 21 days. The LTM alert zone will have
                three distinct color-coded subzones: green, yellow, and red. In the example, each
                subzone will be seven days in length. Additionally, there will be a zone dedicat-
                ed to an order that is late. A notification is given to the planner/buyer each time
                the part enters a subzone. Green zone entry = 21 days in advance of due date; yel-
                low zone entry   14 days in advance of due date; red zone entry   7 days in
                advance of due date; late    an order that is past due. These notifications are
                intended to prompt planning and purchasing personnel to follow up and docu-
                ment the status of these orders beginning at a reasonable time frame in advance
                of the order being due.

             In traditional planning systems there is very little done about the management of
        these types of parts. They are managed by due date with no formal system of visibility
        and proactive management to reflect real priorities. The assumption remains that all the
        parts will be available by the release time of the order that needs them. The problem is
        identified only when the part is late. Orders using that part then are possibly released
        short those parts, causing possible rework on the shop floor and increasing work-in-
        process. Alternatively, some companies will begin to pull parts ahead of time to identify
        this kind of shortage. This process results in a storehouse of partially filled kits and a
        manual system to track the missing parts. Robbing from one pre-pulled kit to fill anoth-
        er kit makes the situation even worse. Additional information on LTM parts will be avail-


           FIGURE 26-3
           Lead-time-managed buffer schema.

                                       63 Day Lead Time
            Order                                                        Order Due
         Release Date                                                      Date

                                                          21 Day LTM Alert Zone

                                                            G     Y      R      LATE

                                                      Notification Notification Notification Notification
   455   456   457   458   459   460   461   462   463   464   465