Page 86 - Orlicky's Material Requirements Planning
P. 86
66 PART 2 Concepts
cumulative lead time (CLT): The longest planned length of time to accomplish the
activity in question. It is found by reviewing the lead time for each bill of material path
below the item; whichever path adds up to the greatest number defines cumulative
lead time.
purchasing lead time (PLT): The total lead time required to obtain a purchased item.
Included here are order preparation and release time; supplier lead time; transporta-
tion time; and receiving, inspection, and put away time. 3
Part 400’s MLT is 4 days, and its CLT is 19 days. The CLT is determined by the path
Part 400 → Part 200 → Part 100. This is the longest total path in the BOM. The 19 days is
calculated by summing all MLTs and the longest-lead-time purchased part (Part 100) in
that CLT sequence. Part 300’s MLT is 7 days, and its CLT is 22 days. Part 300 has a
straight-line BOM, so determining the CLT is much easier because it is the only path in
the BOM. Please note that in this example the parent-to-component usage in all BOM
relationships is 1:1.
A routing is “information detailing the method of manufacture of a particular item.
It includes the operations to be performed, their sequence, the various work centers
4
involved, and the standards for setup and run.” Together, the BOM and the routing paint
a relatively complete planning picture for the total requirements (materials and capacity)
for all parent items and the part’s contribution to the total requirements scenario (capac-
ity and materials).
In this example, no run rates and setup times have been defined. These are not rel-
evant for this simple example. As demonstrated in Figure 4-6, in order to make Part 400,
Part 100 must be purchased and introduced into the process. This takes ten days to
accomplish. The work in process passes through a sequence of three resources (A → B →
FIGURE 4-6
Routings for Part 300 and Part 400.
5 Days 7 Days
Part 100 A B C Part 200 D E F Part 300
Purchased Component Parent
PLT = 10 days
Part 50 G E Part 400
Purchased Parent
PLT = 7 days
4 Days
3 Ibid, p. 112.
4 Ibid, p. 121.