Page 90 - Orlicky's Material Requirements Planning
P. 90

70                                                                  PART 2   Concepts


           FIGURE 4-11

           Part 300 compressed lead time—second iteration.
                            5 Days                                7 Days


           Part 100     A      B      C        Part 200     D       E     F       Part 300
           Purchased                          Component                            Parent
         PLT = 10 days

                                                Part 50       G         E         Part 400
                                               Purchased                          Parent
                                               PLT = 7 days
                                                                   4 Days
           FIGURE 4-12

           Part 400 compressed lead time—second iteration.
                            5 Days                                7 Days


           Part 100     A      B      C        Part 200     D       E     F       Part 300
           Purchased                          Component                            Parent
         PLT = 10 days

                                                Part 50       G         E         Part 400
                                               Purchased                          Parent
                                               PLT = 7 days
                                                                   4 Days
        desired benefit. The only way to compress the Part 400 lead time further is to also place
        a stock buffer at the Part 50 position. This is depicted in Figure 4-13.
             The benefits of this strategy include the following:
             ■ Leads times are significantly compressed. In this case, this strategy will work if
                the customer tolerance times are greater than seven days for Part 300 and greater
                than four days for Part 400.
             ■ Supplier variability relative to both Part 100 and Part 50 now has been removed
                from the lead-time-to-market equation.
             ■ Critical resource E is now better protected from all upstream disruptions.
             ■ Stocking at Part 200 allows that inventory to be leveraged against both Part 300
                and Part 400 requirements.

             The potential risks include the following:
             ■ Without a buffer at Part 100, the front side of the plant is subject to supply dis-
                ruption, which could affect the scheduled activity of these resources.
             ■ Without a buffer at Part 100, the stock position at Part 200 has to be sized for a
                lead time of 15 days.
   85   86   87   88   89   90   91   92   93   94   95