Page 87 - Orlicky's Material Requirements Planning
P. 87

CHAPTER 4      Inventory in a Manufacturing Environment                          67


        C) to transform it into the component Part 200. This can be accomplished reliably in five
        days. This reliability can be affected by finite capacity, quantity, quality, other orders,
        machine breakdown, etc. For this simple example, the assumption is made that the
        process can be completed reliably in five days.
             Part 200 is a point of divergence. A divergent point means that Part 200 can be direct-
        ed into different manufacturing paths. A divergent point represents a commitment that
        cannot be practically or cost-effectively reversed. An example would be the introduction
        of a log into a plywood facility, in which the first step is to peel the log into veneer. This
        decision precludes the log from being used or redirected into dimensional lumber. For
        this example, Part 200 can be directed to resource D, where it will then pass through
        resources E and F to be made into Part 300. This can be accomplished reliably in seven
        days. Part 200 can also be combined with purchased Part 50 at resource G. Resource G
        processes this work and forwards it to resource E to complete the process of producing
        parent Part 400. This can be accomplished reliably in four days.
             In this example, resource E is a critical resource that should be carefully protected
        owing to its importance in the overall process. In this case, that protection must minimize
        disruption that is passed to it from preceding areas. This is a consideration for our stock-
        ing strategy. Resource E has been shaded to denote its special status.
             Consider Figure 4-7 with no stock held at any level. This would be a complete make-
        and-purchase-to-order environment. The CLT paths for both Part 300 and Part 400 are
        laid over the routing. As mentioned earlier, in the case of Part 300, the CLT is 22 days. The
        22-day lead time is calculated by adding the PLT of Part 100 (10 days) and the total time
        it takes to move from resource A through resource F (12 days). In Figure 4-8, the case of
        Part 400, the path is also defined by the Part 100 leg of the BOM path because that is the
        longer of the two legs.
             Given the current competitive position, the customer tolerance time must be con-
        sidered. In this example, the company can have zero inventory if the customer tolerance





           FIGURE 4-7
           Cumulative production lead time for Part 300 with no stock.

                            5 Days                                7 Days

           Part 100     A      B      C        Part 200     D       E     F       Part 300
           Purchased                          Component                            Parent
         PLT = 10 days

                                                Part 50       G         E         Part 400
                                               Purchased                          Parent
                                               PLT = 7 days
                                                                   4 Days
   82   83   84   85   86   87   88   89   90   91   92