48    Pipeline Rules of Thumb Handbook


































           The arc subtended for any angle is directly proportional to
         radius:

           1 inch   0 7432 inches
                     .
                  =
          24 inches     Arc
                         =
                .
             Arc =  0 7432 ¥  24 17 13  16 ≤
         Average pipelay table—Underground

                            Linear feet of pipelay per ten (10) hour day in trench in level, rock-free terrain

                                                   PIPE WALL THICKNESS IN INCHES
                       Nominal      0.000       0.251      0.376       0.501       0.626       0.756
                       Pipe        through     through    through     through     through    through
                       Size         0.250       0.375      0.500       0.625       0.750       1.000

                        4          10,800      10,500      10,300       —           —           —
                        6           9,600       9,400       9,210       —           —           —
                        8           9,120       8,900       8,720      8,550        —           —
                       10           8,900       8,760       8,580      8,410        —           —
                       12           8,600       8,400       8,230      8,070       7,910        —
                       14           8,400       8,230       8,160      8,000       7,840        —
                       16           8,000       7,840       7,680      7,530       7,380       7,230
                       18           7,800       7,640       7,500      7,350       7,200       7,050
                       20           7,400       7,250       7,100      6,960       6,820       6,680
                       24            —          6,600       6,470      6,340       6,210       6,080
                       30            —          6,000       5,880      5,760       5,640       5,530
                       36            —           —          5,400      5,300       5,200       5,090
                       42            —           —          4,800      4,700       4,600       4,500

                       Productivity will vary where different types of terrain or rock are encountered.
                       Above footage is based on installing double random joints of pipe.