Page 68 - Pipeline Rules of Thumb Handbook
P. 68

Construction  55

           or relocated so that bicycles, becaks, and water buffalo would           Construction
           have easier access.
             It was determined that 4ft of cover was required to protect  The design package to the field should include drawing
           the line from excessive wheel loads (people-packed buses and  of new profiles, stations, tables of new pipeline elevations,
           trucks). This means the line must be lowered 7ft (Figure 1).  trench elevations, and a very detailed construction se-
           The pipe is Grade B, allowable bending stress is 10,000psi,  quence. The following may be used as a guide for construc-
           and crossing width is 50ft. To calculate minimum bending  tion:
           radius, total transition length, and deflections at 25-ft inter-
           vals, use:                                             • Starting at one end of transition, dig 40ft of trench under
                                                                    the line. Leave 10ft of soil for pipe support. Dig another
                               )( )
                 ¢
                            ,
           REC S = (29 000 000 18 10 000  = 52 200 in.              40ft, repeat until opposite end is reached. When com-
                        ,
                                             ,
             =
                                      ,
               ,
             = 4 350 ft (min. )                                     plete, 10-ft soil plugs are supporting the line at 50-ft
                                                                    centers.
           Total transition length = ()+ 50 ft
                               4
                                 X
                                                                  • Clean the line between soil supports, take ultrasonic
           Y = 70 .  ft 2  = 3 5 .  ft                              test (UT) readings, and install sleeve where required.
                    -
           X = 2 RY Y 2                                             Add primer and tape wrap between supports, main-
                                                                    taining station numbers and elevation points on the
                                 2
           X = ()(4 350 )(3 5 .  ) -(3 5 .  ) = 175 ft              line.
                    ,
                2
           Total transition length = 750 ft                       • Add 12in. of sand or soil/sand pre-mix to bottom of

                                                                    trench and compact to proper trench bottom elevation
             It is suggested that field personnel start survey (elevations)  (profile elevation minus pipeline diameter).
           500ft left of crossing centerline and stop at station 10 + 00.  • Install 6-in. ¥ 6-in. wooden blocks every 50ft (between
             Deflections at 25-ft intervals are calculated from Eq. 3  soil plugs) to support the line.
           (Figure 3), and a table is prepared accordingly (Table 1). Note  • Remove soil plugs and complete line cleaning, UT
           that calculations for Y are required for 175ft only. Since the  readings, sleeve installations, tape wrapping, and trench
           curve is then inverted (Sta 3 + 00 to Sta 4 + 75), results are  preparation.
           subtracted from 7.0ft, working backwards, to arrive at true  • Check elevations of new trench bottom, adjust as
           deflection or drop. For example, deflection at Sta 4 + 50 = 7.0  required. Check tape wrap with holiday detector if
           - 0.07 = 6.93, etc.                                      desired.
                                                                  • Starting at one end, use six sidebooms to raise approxi-
             Example 2. Given following elevations, is pipeline being  mately 250ft of line off its supports. Remove 6in. (or less)
           dropped too suddenly, and will it become over-stressed   of blocks on outside supports and 12in. of blocks on all
           between stations 1 + 00 and 1 + 50 (Figure 2)?           inner supports. Lower line onto supports.



















           Hand cleaning. The 30-in. and 36-in.  Lowering lines. The two lines, full of  Gradual lowering. A full sweep of the
           crude lines were cleaned by hand to  crude oil, are gradually lowered with the  total transition length is made by lower-
           expose corroded areas and prepare for  use of six sidebooms.            ing each line 6in. or less at a time. The
           tape-wrapping.                                                          procedure is repeated until the lines
                                                                                   finally reach desired profile elevations.
   63   64   65   66   67   68   69   70   71   72   73